Progress on site continues briskly, as we move to the final stages of the external build and onto the internal fit out. The distinctive red roof is now almost complete – using BSW’s IRO timber. The wooden roof was chosen because of its significantly lower carbon impact compared to other roof finishes. The Fakro rooflights[…]
Category: Uncategorized
Rapid progress on site: Week 3
After six days on site, the roof panels were on and they were all set for the windows. Days 7-12 saw the NorDan windows going in, the outer membranes being put in place and battens now being put on for inside and outside cladding. The team from Urban Union – part of the Robertson Group[…]